Campus complex

swcc1

This facility houses both administrative offices and a private school, operating approximately 12 hours per day, five to six days per week. Rising energy costs had a devastating effect on their operating budget, while frequent utility outages interrupted operations.

Cogeneration is a versatile technology applicable to a wide variety of applications. Our solution for this facility was a 440 kW on-site cogeneration system.

It provides the facility with a steady supply of power in parallel with the utility grid and provides over $225,000.00 a year in energy cost savings.

Overview:

  • 440 kW natural gas packaged cogeneration system
  • 110 Ton absorption chiller
  • Annual Savings: $225,000.00
  • 7 Year Savings: $1,575,000.00
  • Payback: 21 months (with rebate)

The system also has improved overall power quality while providing protection from utility outages.

This application is real-world proof that cogeneration is not just for industrial or round-the-clock applications. Even with relatively low annual run-time hours, this facility realizes substantial energy savings and a rapid payback. This entire turnkey project, including engineering, permitting and installation, after rebate, was under $400,000 providing a payback of less than two years!

Let Flexible Energy find the right solution for your organization. Our unique approach and extensive problem solving abilities have made energy savings of up to 50% a reality for a wide range of businesses and organizations including manufacturing, health-care, resort & hospitality, public & private schools & universities as well as churches, retirement homes and dairies.

See how much you can save – contact us today for a free, no-obligation consultation.